Sitework and Stormwater System

Crews have started setting the structural steel for side wall of 20,000 sf metal building...

Project Update – Ford PEMB

Crews finished roof purlins and have started installing doors on west side of building at...

Ribbon Cutting Ceremony

Ribbon cutting ceremony today for Trailhead Splash Pad. Such a great project to have been...

Project Update – Interior Painting

Interior painting has started at ASA Fine Arts Building. Energetic wall colors make all the...

Body Shop Project Update

Roofing, wall sheeting, interior framing and overhead doors are complete at Jarrett-Gordon Ford of Davenport. Electricians...

Jarrett Gordon – Progress Update

Life Expectancy Of An Asphalt Parking Lot A properly installed asphalt parking lot with regularly...