
Project Build Blog
Barney’s Pump – Completed Project
This building is the future home of Unitron Controls, they build control panels for lift...
Slab & Completed Trench Drain
At the Lakeland Linder Regional Airport, the slab has been poured and trench drain installed...
Dr. Siddiqui Office/ Lab- Progress December 2015
The outside of the building is almost complete. Sitework is done, landscaping is being installed...
Foster Hangar Progress Update February 2016
We have finished sheeting the exterior walls and roof of the building, and are now...
Adamson Addition – Slab
Here is a picture of the finished concrete pour for our clients at Adamson &...
Oakley Transport – Progress Update
Progress Photo Update at Oakley Transport: Interior finish work has been completed and the interior...
Cedar Trail – Progress Photos
Large overhead doors, storefront and exterior site work in progress. Electricians are running light fixtures...
Adamson Roofing Trusses
Progress Photo Update: We set roof trusses at Adamson using a thirty ton crane...
Trailhead Splash Pad – Beginning of Project
Design/ Build project of Trailhead Park Splash Pad. This splash pad will incorporate mounted spray...
O.C.A Progress Update
Progress Update: Our Children’s Academy- Sitework being performed at O.C.A. typically this includes grading, excavation...
Adamson Addition Nearing Completion
This office addition project was started April 24th and will be completed July 22nd...