Since our last update, painted drywall and a ceiling grid have turned an open steel shell into a working office at Cornelius Welding in Lakeland, Florida. Since the steel frame went up this summer, the A.O. Wagner team has carried CWI’s new 120′ x 50′ Whirlwind pre-engineered metal building through enclosure, rough-ins, and drywall, and the finish line is in sight.

Site Work Out Front

From the street, final grading is wrapping up across the property in preparation for asphalt.

Along the right of way, crews tied the new concrete curb into the existing road for a clean, finished transition. A new retaining wall holds back the grade change, and a stormwater cleanout is installed and ready. Sod is next for this area.

Next up was the asphalt. Crews laid the new driveway and followed close behind with the roller to compact it smooth and solid.

A Polished Front Entrance

The covered front entrance now features storefront windows and doors installed by Central State, giving the front a clean and professional finish.

Flex Space Ready for Work


Inside, the flex space is complete. American Roll Up Door installed the building’s roll-up doors, which give the warehouse direct access to the new driveway.

Looking from the office side, the connection between both halves of the building is easy to see. Electrical trim is up next for the space.

Power is already in place, with both the interior electrical panel installed and a 208/120 three-phase meter box mounted outside.

Inside the Office Build-Out

Rough framing, electrical, and mechanical work are all finished throughout the office side of the building. Drywall is hung and painted, and the ceiling grid is going up. In the conference room and private offices, crews will complete electrical and HVAC trim-out, then install ceiling tiles, flooring, and vinyl baseboards.

The open area at the front of the building will hold cubicles for CWI’s team. After electrical trim-out, it will receive ceiling tiles, carpet tile flooring, and vinyl baseboards for a finishing touch.

In the restroom, the team installed fixtures and tile flooring, and will install ADA accessories next.

The Home Stretch

With trim-outs, flooring, ceiling tiles, and sod still to go, CWI’s new facility is on track for completion at the beginning of November. Built on a frame by Whirlwind Steel—a manufacturer producing award-winning custom metal buildings since 1955—this facility will give CWI a durable, purpose-built home for years to come.

Thinking About a Ground-Up Build?

From an empty lot to a finished office and warehouse, A.O. Wagner Construction manages every step under one roof. If your business is ready for a new facility, let’s start the conversation.

A.O. Wagner Construction provides full-service general contracting, management services, and design/build construction throughout Central Florida. We love serving Winter Haven, Lakeland, Davenport, Haines City, Auburndale, Avon Park, and neighboring areas! Follow our Project Build Blog to see more of our past projects. For more information, please email us at info@aowagnerfl.com or call 863-299-4444.