Back in early January, A.O. Wagner Services broke ground on our project to build Winter Haven’s new Jarrett Gordon Lincoln Dealership. We’ve made great progress so far on the approximately 7,000-square-foot-new building and exterior. Previously, we’ve done demolition of the existing building, site work to make the ground level, and installed a new concrete foundation and fire-rated block wall. Now, we have some updates for you on our latest progress.
First, let’s take a look at the current state of the exterior of the building. From here, our next steps are to install the storefront glass and apply the finishes to the exterior.
We applied spray foam to the ceiling, which you can see here.
The interior showroom is shaping up nicely with the metal stud framing in place, HVAC ducts installed, and insulation installed in the exterior framing.
This shot of the interior showroom offers a great view of the structural steel we’ve installed.
Here we can see the framing for the offices, where we’ve roughed in HVAC and electrical and installed insulation.
We’re also making great progress on the car service drive, where we completed the ceiling R/I and are ready for metal finishing next week.
Finally, we put in an electric charging station, which is now operational.
We expect to complete this project by November/December of this year. No matter how big or small the job, we always provide the highest quality of work. If you need a job done right and you’re in Central Florida, contact us today to talk to our team of professionals.
A.O. Wagner provides full-service general contracting, management services, and design/build construction throughout Central Florida. We love serving Winter Haven, Lakeland, Davenport, Haines City, Auburndale, Avon Park, and other areas throughout Central Florida! Follow our Project Build Blog to see more of our past projects. For more information, email us at info@aowagnerfl.com or call us at 863-299-4444.